S. K. Samanta & Co. (P) Ltd. · Project Controls

Engineering Drawing Control

Weekly review · · Project 183 NMDC Kirandul Crushing Plant
Key messages this week
    Project
    183 · Kirandul New Crushing PlantDeposit 14 & Deposit 11C · Bailadila Iron Ore Mines
    Client
    NMDCConsultant: M.N. Dastur
    Scope
    DrawingsDesign & engineering
    Reporting week
    Exhibit 01

    Discipline status

    click any figure to filter the register

    Source: ERP drawmaster (register, discipline, active status) · drawrepledg (events) · drawrec (approval verdicts) · ERP export 2026-09-03
    Exhibit 02

    Approval versus information category

    the two categories the contract prices separately

    Source: ERP drawmaster.draw_cateai · bsgroup billing groups A.1.x / B.1.x and A.2.x / B.2.x · ERP export 2026-09-03
    Exhibit 03

    Ageing by owner

    three clocks, three different owners

    Source: ERP drawrepledg latest event per drawing · planned dates from drawmaster.schsubmclient_dt · ERP export 2026-09-03
    Exhibit 04

    Monthly throughput

    events, not unique drawings

    Submissions to client Approvals received
    Source: ERP drawrepledg submission and approval events by calendar month · ERP export 2026-09-03
    Exhibit 05

    Backlog ownership

    design vendor recorded on the register

    Source: ERP drawmaster.vendor_cd on drawings with no recorded event · ERP export 2026-09-03

    Statuses are the ERP's own. Approved and Approved as Noted are the verdicts recorded in drawrec.remarks (normalised from APPROVED / APPD / APPD./NO COMMENTS and APPROVED AS NOTED / AAN). Inactive is drawmaster.active_stat = NO. Under review and Commented are the drawing's latest event in drawrepledg, and Not submitted means no event of any kind.
    Source. ERP export dated 2026-09-03 — drawmaster, drawrepledg, drawrec, drawcomdet, bsgroup. Scope is the ERP register only: 1,243 unique drawings, of which 205 are inactive. A further 60 drawings have events but no register entry and are excluded.
    Category values come from billing groups A.1.x / B.1.x (approval) and A.2.x / B.2.x (information). The billing schedule is still being entered in the ERP, so treat those two figures as indicative.
    Read-only. Rebuilt from each weekly export — nothing is entered here and nothing is stored.