S. K. Samanta & Co. (P) Ltd. · Project Controls

Project Overview

Management summary · · Project 183 NMDC Kirandul Crushing Plant
What matters this week
    Project
    183 · Kirandul New Crushing PlantDeposit 14 & Deposit 11C · Bailadila Iron Ore Mines
    Client
    NMDCConsultant: M.N. Dastur
    Covers
    Three functionsengineering · procurement · billing
    Reporting week

    Client-side figures come from the accounts ledger, vendor-side figures from the purchase order and dispatch registers. Site inventory and labour are not covered — the reason is in Exhibit 05.

    Exhibit 01

    The three functions

    each has its own weekly report

    Source: the three weekly function reports, all built from the same ERP export dated 2026-09-03
    Exhibit 02

    Money in against money committed

    what is still to come, on both sides

    Source: client side from ERP fatrans accounts 4101, 1481, 1482, 2952, 2922, 2936, 2937, 2441 · vendor side from porderdet ORD_VALUE against podispreg dispatched quantity · ERP export 2026-09-03
    Exhibit 03

    What needs a decision

    ranked by what it costs to leave alone

    Source: drawn from the three function reports; each item traces to a named table and column there · ERP export 2026-09-03
    Exhibit 04

    Activity pulse

    is each function still being recorded?

    Source: monthly count of recorded events per function — drawrepledg for engineering, podispreg for procurement, fatrans for billing · ERP export 2026-09-03
    Exhibit 05

    What this report cannot see

    stated, not worked around

    Source: fields tested and found empty or stale in the ERP export dated 2026-09-03

    This page is a summary of three reports, not a fourth source. Every figure on it is produced by the weekly Engineering Drawing Control, Procurement & Delivery Control and Client Billing & Collection reports, all built from the same ERP export. Where a number needs tracing, it traces there, and from there to a named ERP table and column.
    The one independent check. Account 4101 totals ₹282,82,89,275.13 across 41 RA bills against a certified RA-41 cumulative of ₹282,82,89,271.94 — ₹3.19 apart, derived from different sources. That agreement is why these reports can be produced from the export alone.
    Two functions are missing on purpose. Site inventory is excluded because the material ledger stops on 30 June while receipts run to 25 August, and the issues table is truncated at exactly 4,000 rows. Labour and measured work are excluded because mesubook and labfl hold no rows at all for this project. Neither is a judgement about the site; both are statements about the data.
    No percentage of contract appears anywhere. projmast.CONTBIL_VALUE is 0.00 and the billing schedule does not reconcile to its own item lines, so there is no honest denominator for a completion figure.
    Read-only. Rebuilt from each weekly export — nothing is entered here and nothing is stored.